Updating actual and remaining duration allows tracking time that has actually been spent from task start or has still been remained till task finish. CentriQS lets you use actual and remaining durations for monitoring employee performance, project progress or other goals.

Actual Duration

Actual duration is the time that has been already spent during the task execution. It can be entered manually or updated automatically. After you save the changes, actual duration will be shown in the ‘Actual’ column.

task actual duration

Enter Actual Duration Manually

You can enter actual duration manually into the ‘Actual’ field. By default when the task is in state ‘Created’, its ‘Actual’ field is disabled. In order to enable it, you need to change task state to ‘In Progress’.

enter task actual duration

Update Actual Duration Automatically

You can update actual duration automatically by clicking the ‘Update’ button. After you do this the system will automatically enter the value which is calculated as the difference between the current date & time and date & time when the task was set to state ‘In Progress’.

update task actual duration

Remaining Duration

Remaining duration is the time that still has been left till task completion. It can be entered manually or updated automatically. After saving the changes, remaining duration is shown in the ‘Remain’ column.

task remaining duration

Enter Remaining Duration

You can enter remaining duration into the ‘Remain’ field. This field is also disabled for tasks in state ‘Created’, so before entering the remaining time you need to change state to ‘In Progress’.

enter task remaining duration

Update Remaining Duration Automatically

Remaining duration can be updated automatically if ‘On Schedule’ mode is on. After you check the ‘On Schedule’ option the system will automatically enter the value which is calculated as the difference between estimated and actual duration.

update task remaining duration

Correlation between States and Remaining Duration

CentriQS automatically correlates task ‘State’ and ‘Remain’ value:

1. When you enter “0” into ‘Remain’ field, task state gets automatically changed to ‘Closed’.

2. When you change task state to ‘Closed’, the value in the ‘Remain’ field gets automatically changed to “0”.

3. When you change the value in the ‘Remain’ field from “0” to certain duration, task state gets automatically changed from ‘Closed’ to ‘In Progress’.

states and remaining duration correlation

Actual and Remaining Duration of Parent Task

Actual and remaining duration of parent task is calculated automatically as the summary of its subtasks’ durations. By default the total task duration (including actual and remaining duration) is shown in days, however you can change the units in Application Menu/Options

parent task actual and remaining duration

Next steps

{

Check out Task Management FEATURES

Watch Task Management Solution VIDEO OVERVIEW

Learn how to manage tasks in KNOWLEDGE BASE

DOWNLOAD CentriQS 30-day Free Trial Version

CONTACT US to get help with Task Management Solution