To show tasks scheduled for the next or last several hours
- In the Tasks view, right-click a column header, click Column/Band Chooser, and then drag Schedule Start and Schedule Finish from the Customization dialog box to column headers.
- Point to the Schedule Start column header, click the Quick Filter icon on its right side, and then select a check box next to required time period (Last 1 hour, Last 3 hours, Last 6 hours, Next 1 hour, Next 3 hours, Next 6 hours).
- Point to the Schedule Finish column header, click the Quick Filter icon on its right side, and then select a check box next to required time period (Last 1 hour, Last 3 hours, Last 6 hours, Next 1 hour, Next 3 hours, Next 6 hours).
Tip You can also set appropriate filter by clicking Filter in the View group on the ribbon.